Materials6 min read

The material specification checklist to attach to every interior quote

Send this list to every vendor before they quote. Identical specifications turn three incomparable estimates into three comparable prices.

The cheapest way to save ₹1–2 lakh on interiors is not negotiation. It is sending every vendor the same written specification before they quote, so nobody can win the deal by quietly quoting a weaker material.

1. Boards and structure

  • Carcass: 18mm BWP plywood, IS:710, brand named, in kitchen, bathroom vanity and external-wall lofts.
  • Carcass (dry zones): 18mm MR plywood IS:303 or HDHMR, brand named.
  • Shutters: 18mm HDHMR or BWP ply as specified per unit.
  • Back panels: minimum 6mm, and 12mm where units carry load.
  • Edge banding: 2mm PVC on all exposed edges, 0.8mm permitted only on internals.

2. Finishes

  • Laminate: brand, thickness (0.8mm or 1mm), and catalogue code per unit.
  • Acrylic: 1mm sheet, brand named — not 'acrylic-finish laminate'.
  • Membrane / PU / veneer: brand, number of coats, and warranty on yellowing or peeling.
  • Internal laminate: white or specified colour on all internal surfaces, not raw board.

3. Hardware

ItemSpecifyQuantity to confirm
HingesBrand, soft-close, clip-onCount per unit
Drawer systemsBrand, tandem box vs metal box, load ratingNumber of drawers
ChannelsBrand, soft-close, telescopicPer drawer
Kitchen basketsBrand, SS 304 vs SS 202, sizesPer unit
Lift-ups / gas strutsBrand and load ratingPer wall unit
Handles / profilesBrand, finish, lengthPer shutter

4. Kitchen specifics

  • Countertop: material (granite / quartz), thickness, brand or quarry, edge profile, and whether skirting is included.
  • Sink and faucet: brand, model, gauge for SS sinks.
  • Chimney and hob: brand, model, suction rating — or explicitly marked as owner's scope.
  • Cut-outs, water-line shifting and drain-point changes: included or excluded, in writing.

5. Site, service and paperwork

  1. 1Electrical points: number, type and location list, with per-point rate for additions.
  2. 2False ceiling: area in sq.ft, gypsum brand, and whether cove lighting cut-outs are included.
  3. 3Painting: brand, product line, number of coats, putty and primer included.
  4. 4Timeline: start date, milestone dates, handover date and delay compensation.
  5. 5Warranty: years on materials, years on hardware, and service turnaround.
  6. 6Payment: milestone-linked schedule with a maximum 10% booking advance.

Audited insight

How to use this

Paste the checklist into your email, ask every vendor to quote against it exactly, and reject any quote that answers a line with an adjective instead of a brand, grade or number.